Corrosion and Scale Monitoring and Inhibitor Injection

refinery

Scope

This  project was proposed to provide a comprehensive package for corrosion and scale monitoring and inhibitor injection in the following fourteen (14) Nos. GC’s at South East Kuwait (SEK) namely GC-1, 2, 3, 4, 6, 7, 8, 9, 10, 11, 19, 20, 21 & 22. The monitoring system was to consist of monitoring access fittings & sampling points. The chemical injection system was to consist of injection points, installation of chemical injection skids, chemical injection pumps, chemical tanks, suitable piping system from pump skids to various injection points. This project involved the installation of transfer pumps skid, suitable piping system to transfer chemicals from transfer pump skids to all chemical injection tanks, drain network, instrument air supply lines, chemical shelters, and eye wash and shower units.

CLIENT

Kuwait Oil Company

KNPC CONTRACT #

29152

VALUE

KD 13,768,588/-